Outside Agency Construction Projects
PSEG Smart Meter Information
Please be advised that residential properties will be receiving letters from PSE&G in the near future informing them that PSE&G is going to begin deployment of smart electric meters in the City of Rahway. These meters will, among other things:
• provide you with more information about your electric use
• allow automatic, near real-time meter reading that will eliminate almost all estimated electric bills
• enable near real-time power outage detection and make storm restoration work more efficient
PSE&G has hired Contact Callers Inc (CCI) to perform the meter installations. Additional information regarding smart meters and their benefits is available at pseg.com/smartmeters as well as in the links below.
- General Project Documents
Elizabethtown (ETG) Pipeline Replacement Project
- General Project Documents
- Location Specific Documents and Information
- Washington Street Gas Main Construction Project - Fact Sheet
- Washington Street Map
Main Installation Projected Start- 9/11/2023 Projected Finish- 9/29/2023
Services & Retirement Projected Start- January 2024 Projected Finish- March 2024
Project limits are as follows:
-Washington Street from Lawrence Street to Paterson Street
The following streets will be affected near the Washington Street:
-Bond Street
-Brady Court
-Columbus Place
-E. Grand Ave
-E. Milton Ave
-Lawrence Street
-Monroe Street
-Montgomery Street
-Park Street
-Paterson Street
-Rutherford Street -Washington Street
- Whittier Street- Gas Main Construction Project- Map
Project Fact Sheet
Neighborhood Notification - Road Restoration Projected Start- 10/23/23 Projected Finish- 11/3/2023 Main Installation Projected Start- 5/17/2023 Projected Finish- 6/19/2023
Services & Retirement Projected Start- 6/2/2023 Projected Finish- 7/21/2023
Project limits are as follow:
-Whittier Street from River Road to Jones Place (Linden Border) - Broad St. & Emerson Ave.- Gas Main Construction Project- Fact Sheet
- Road Restoration (Milling/Paving) Projected Start: 10/02/2023 / 10/04/2023 Main Installation Projected Start- 3/24/2023 Projected Finish- 4/25/23
Services & Retirement Projected Start- 5/2/2023 Projected Finish- 6/19/2023 - Project limits are as follow:
-Broad Street from W. Milton Ave. to W. Lake Ave.
- Clinton Street from Jaques Ave. to Broad St.
- E. Emerson Ave. from Broad St. to Fulton St.
- Fulton Street from E. Emerson Ave. to E. Hazelwood Ave.
- Georgia Street from W. Milton Ave. to W. Emerson Ave.
- Maple Ave. from Jaques Ave. to Broad St.
- W. Emerson Ave. from Jaques Ave. to Broad St.
- W. Albert Street (Broad St. Intersection)
- W. Stearns Street (Broad St. Intersection)
- W. Lake Ave. (Broad St. Intersection) - E. & W. Grand Ave. Gas Main Construction Project - Fact Sheet
- E. & W. Grand Ave. Map
Main Installation Projected Start - Completed 9/21/2023
Services & Retirement Projected Start- Underway Projected Finish- End of October 2023
Project limits are as follows:
-East and West Grand Avenue from Whittier Street to Route 1&9
The following streets will be affected near the Grand Avenue intersections:
-Allen Street
-Bridge Street
-Elizabeth Avenue
-Lawrence Street
-Linden Place
-Lufberry Street
-Montgomery Street
-Newton Street
-Patterson Street
-Rutherford Street
-E. Scott Avenue
-Tara Court
-Teneyke Place
-Turner Street - Bryant Street Gas Main Construction Project- Fact Sheet
Main Installation Projected Start- 4/10/2023 Projected Finish- 5/10/23
Services & Retirement Projected Start- 8/15/2023 Projected Finish- 11/1/2023
Project Limits are as follows:
- Bryant Street from W. Milton Ave. to W. Inman Ave.
- Coddington Street from St. Georges Ave. to Jaques Ave.
- Forbes Street from Bryant St. to Jaques Ave.
- Maple Ave. from Bryant St. to Jaques Ave.
- Oak Street from Bryant St. to Jaques Ave.
- Stanton Street from Bryant St. to Jaques Ave.
- W. Emerson Ave. from Bryant St. to Jaques Ave.
- W. Hazelwood Ave. from Bryant St. to Jaques Ave.
- W. Inman Ave. from Bryant St. to Jaques Ave.
- W. Lake Ave. from Bryant St. to Jaques Ave.
- W. Milton Ave. from Bryant St. to Jaques Ave.
- W. Stearns Street from Bryant St. to Jaques Ave.
- Walters Street from Bryant St. to Jaques Ave.- Westfield Ave - Fact Sheet - GAS WORK COMPLETE - Road Restoration Complete
Project limits are as follows:
- Westfield Ave from Madison Hill Rd to Fowler Pl
- Madison Hill Rd from Westfield Ave to Washington
- Kline Pl from Westfield Ave to Stone St
- Madison Ave from Westfield Ave to ~150' south of Westfield Ave - W. Scott Ave & Linden Ave - Fact Sheet - GAS WORK COMPLETE - Road Restoration Complete
Project limits are as follows:
- Linden Ave from West Scott Ave to Elizabeth Ave
- Egolf Drive (Total)
- Price St from West Scott Ave to Linden Ave
- West Scott Ave & Allen St from intersection to ~20' north on Allen St
- West Scott Ave & Elizabeth Ave from intersection to ~39' north on Elizabeth Ave - Whittier St & Linden Ave - Fact Sheet - GAS WORK COMPLETE - Road Restoration Complete
Project limits are as follows:
- Whittier St from Koenig Pl to West Scott Ave
- Whittier St from Raleigh Rd to ~111' south of Lower Alden Dr and Donald Ave
- Raleigh Rd from Whittier St to Knapp Dr
- Canterbury Lane from Raleigh Road to Lower Alden Dr
- Knapp Dr from Linden Ave to Koenig Pl
- Booth Ct (Total)
- Koenig Pl from Whittier St to Knapp Dr
- W Hazelwood Ave (Bryant St to Fulton St) - Fact Sheet - Road paved by Union County (updated 3/10/23)
Project limits are as follows:
- West Hazelwood Ave from ~30' west of Bryant St to Penn St
- Bryant St from ~20' south of West Hazelwood Ave to ~20' north of West Hazelwood Ave
- Jaques Ave from ~20' south of West Hazelwood Ave to ~20' north of West Hazelwood Ave
- Broad St from ~20' south of West Hazelwood Ave to West Hazelwood Ave - Thorn St & E Lake Ave - Fact Sheet - GAS WORK COMPLETE - Road Restoration Complete
Project limits are as follows:
- Thorn Street from East Lake Ave to East Hazelwood Ave
- Hazel Pl from East Albert St to East Hazelwood Ave
- Brookfield Pl from Hazel Pl to Main St
- East Albert St from ~14' west of Thorn St to Main St
- Main St from East Stearns St to Sterling Pl
- Leesville Ave from East Hazelwood Ave to ~568' south of East Hazelwood Ave
- East Hazelwood Ave from Leesville Ave to ~41' east of Leesville Ave
- East Stearns St from Thorn St to Main St
- Thorn St from East Stearns St to East Lake Ave
- East Lake Ave from New Brunswick Ave to Main St
- Regina Ave from Holly Pl to Main St
- Holly Pl from East Lake Ave to Regina Ave
- Ferndale Pl from East Lake Ave to Regina Ave
- Laurel Pl from East Lake Ave to Regina Ave - Pierpont St - Fact Sheet - GAS WORK COMPLETE - Road Restoration Complete
Project limits are as follows:
- West Emerson St from Bryant St to West Milton Ave
- Maple Ave from Bryant St to Pierpont St
- Pierpont St from St. Georges Ave to West Milton
- Stanton St from Bryant St to Pierpont St
- West Stearns St from Bryant St to Pierpont St
- West Lake Ave from Bryant St to St. Georges Ave
- Oak St from Bryant St to Pierpont St
- Walters St from Bryant St to Pierpont St
- Forbes St from Bryant St to Pierpont St
- Westfield Ave - Fact Sheet - GAS WORK COMPLETE - Road Restoration Complete
Rail Projects
- Amtrak Closure of W. Hazelwood Avenue - COMPLETE